Floor slab depression.
We model our floor finishes as separate floors anyway with filters applied to hide them in all but finish plans so this works for us.
I am having trouble creating a slab depression.
Use floor slab depressions in specific areas or rooms to direct water into drains by sloping the floors.
When high slump structural lightweight concrete is vibrated some of the mortar in the slab is likely to separate and move toward the bottom of the slab.
Floor slab depressions 1.
Create a floor based family and setting up parameters.
That is nothing but a void form hosted by the slab floor which creates the depression then drop the tile floor in the void.
Clarification if a depression constitutes a hole or unprotected side edge and associated fall protection requirements.
Kamran s option also works pretty well or you could use a shaft opening if nothing else that s cut by a shaft needs to exist in that depression.
Or more correctly there seems to be a number of ways to do it and i am not sure which is best.
Use floor slab depressions in specific areas or rooms to direct water into drains by sloping the floors.
Description used in the construction industry that references the reduction of the depth or thickness of a concrete slab.
To insure that the floor of prefabricated rooms and access floors are level with the corridor floor b.
This separation will be worse if the vibration is excessive.
To provide space for the installation of shielding in certain areas and.
To provide clearance for equipment c.
Any help with best practice here is greatly appreciated.
To insure that the floor of prefabricated rooms and access floors are level with the corridor floor b.
I created a 12 concrete slab.
A sdvosb service disabled veteran owned small business.
Reinforcing steel is apt to transmit vibration particularly if the vibrator happens to be laid directly on the steel mat.
Then create a new floor of 8 thickness and draw it inside the hole of the first floor.
To provide clearance for equipment.
In it i need a 4 depression.